Goal for the sprint: detailed and cleaned Solution backlog in JIRA allocated to Sprints; all internal project systems are set.
Set up and prepare the Pfx application for starting the developments.
Actions:
-
Making sure that all user stories are clearly defined with acceptance criteria and are allocated to Sprints
-
In your Jira project, make sure you setup the estimation statistic properly in hours/MDs, not in story points
-
Revisit the sprint and project timeline after user story refinement
-
Provide support and work with customer on data interfaces
-
Plan and prepare Setup Sprint including stand ups and demo calls
-
Prepare a protocol about the agreed points during the foundation week that customer should confirm in written form
-
Make sure that the customer has provided the sample data that is sufficient for starting the configuration.
-
Make sure that the sample data has been sent to Pfx team (manual – small real data set).
-
Make sure that tables in Pfx for uploading the data are ready.
-
Make sure that customer has access to the QA partition and know how to access the application.
-
Assure that acceptance criteria for feature Sprint #1 are confirmed by Pfx and Customer and uploaded in JIRA.
Artifacts:
-
JIRA Project
-
Data Specification document
-
RAID Log
-
DEV partition (SA/CE should have credentials)
-
QA partition (SA/CE should have credentials)
Checklist for Preparation sprint:
-
JIRA is set up with tasks and time estimations in hours/MDs (not in story points!)
-
Customer has access to JIRA and knows how to use the system.
-
You agree on the timeline for the project, and it is documented in communication with the customer.
-
The sprints or timeframe for implementation is revised.
-
The user stories and data interfaces specified for being developed (including non-functional user stories).
-
The team resources are available during the sprints.
-
You scheduled a weekly call with the customer for the project updates.
-
You watched the budget used on this stage and manage it within performance corridor.
-
You keep Project Confluence page up to date
-
The Configuration sprint is planned and will kick off right after Preparation sprint.